News: Centre Advises RERAs to Extend Projects by Four Months-31-07-2026

State Real Estate Regulatory Authorities (RERAs) have been advised by the Centre to extend the registration and completion timelines of eligible real estate projects by four months because of disruptions linked to the ongoing West Asia crisis.

The advisory, issued by the Ministry of Housing and Urban Affairs (MoHUA) on July 31, applies to all registered projects whose original, revised or extended completion date falls on or after February 28, 2026. It gives developers relief from penalties for delays caused by circumstances beyond their control.

To avoid procedural delay, the Ministry recommended that each State RERA issue a single order granting the extension instead of asking for separate applications project by project.

The Ministry said the situation in West Asia has disrupted global supply chains, causing shortages of construction materials and affecting timely execution. It cited Section 6 of the Real Estate (Regulation and Development) Act, 2016 (RERA), which permits extension of a project’s registration on account of Force Majeure, a term that includes "war" affecting regular development. Under Section 7(3), it noted, the Authority may let a registration remain in force, instead of revoking it, on terms it considers appropriate in the interest of allottees.

Developers’ bodies welcome step

Shekhar G Patel, president at CREDAI National, called the advisory a positive and timely step in line with the sector’s request. He said the industry had faced significant difficulties with material supply chains and labour availability, and that the extension would help align completion timelines with current conditions. A common order by State RERAs, he added, would ensure uniform implementation while protecting all stakeholders, including homebuyers, and maintaining the sanctity of the RERA framework.

Parveen Jain, president, NAREDCO, described the advisory as timely and pragmatic. He said the geopolitical situation had significantly affected the availability and cost of construction materials, causing unavoidable delays, and that recognising this under RERA’s Force Majeure provisions was balanced and much needed. He urged all state RERAs to implement it "in letter and spirit", saying timely extensions would also protect homebuyers by enabling orderly completion, reducing litigation and giving greater certainty.

NAREDCO said uniform implementation across states would maintain project momentum, ease regulatory hurdles and strengthen homebuyer confidence.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.