News: Gurugram-Pataudi-Rewari Highway Deadline Extended to Sept 30-21-07-2026

The 46.1-kilometre Gurugram-Pataudi-Rewari highway has a new completion date of September 30. The National Highways Authority of India (NHAI) extended the deadline on Monday, citing a bitumen shortage linked to the ongoing conflict in West Asia and pending work on three structures. It is the sixth extension for a project originally due in November 2023. The earlier deadline was March 2026.

A senior NHAI official, asking not to be named, said around 84% of the work is done, with major flyovers, underpasses and culverts built. Three flyovers between Wazirpur and Dwarka Expressway will open by the end of this month and the flyover on Dwarka Expressway will be finished by September 30. He said NHAI is trying to source imported bitumen because the war in the Gulf has made procurement difficult.

According to officials, pending structures include flyovers at Bawra, Bakipur and Jamalpur and a railway overbridge (ROB) at Pahari village. The official said about 70% of work on the pending structures is complete. The railways have permitted casting of girders on the ROB, but timing depends on their nod based on train movement.

Awarded in 2020, the project originally covered 81 culverts, 23 vehicular underpasses, one railway overbridge and two flyovers. Around 10 structures were added later, contributing to delays, officials said.

The highway starts at Sector 84 on Dwarka Expressway and runs to Rewari via Wazirpur village on the Gurugram-Pataudi Road.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.