News: KRERA Orders Total Environment to Pay Rs 70 Lakh for Delay-23-04-2026

A developer cannot blame a change of ownership for failing to deliver on time, the Karnataka Real Estate Regulatory Authority (KRERA) has held, directing Total Environment to execute the sale deed and pay nearly Rs 70 lakh as compensation to buyers of a luxury villa in north Bengaluru delivered two years late.

The villa is in the ’After the Rain Phase 1’ project and has a saleable area of 3,090 sq ft and carpet area of 2,475 sq ft. The original owners signed a sale-and-construction agreement on July 2, 2014 and paid over Rs 3.21 crore. Eight years later they sold it for Rs 4.77 crore to the present complainants through an assignment deed executed in October 2022 with the developer’s consent.

The buyers told KRERA that under the agreement and assignment terms, the developer had to finish construction, obtain the Occupancy Certificate (OC) and hand over possession by May 31, 2023. They said the timeline was instead pushed repeatedly, to September 2023-December 2023, March 2024, June 2024 and November 2024, on false assurances that the villa was nearly ready. Photographs showed construction was still incomplete in January 2025, they said. They approached the authority last year.

The developer argued that the delay arose from the ownership transfer process and the buyers’ failure to pay the final instalment. It also cited customisation work sought by the buyers and said only ’minor works’ remained.

KRERA rejected this. Its order said the contention that construction halted because of the resale cannot be a valid ground, since the promoter must ensure continuity of construction irrespective of a change in allottees. It called it a settled position that transfer or assignment of a unit does not absolve the promoter of the obligation to complete the project within the agreed timeline.

The authority found the delay was mainly the developer’s responsibility, though the complainants contributed slightly by not paying the balance on time.

It directed the developer to pay delay period interest on the consideration amount of Rs 3.3 crore at SBI MCLR+2% from May 2023 till July 2025, when possession was offered, for Villa/Unit No.0114 (Villa No.84 as per the BDA sanctioned building plan). Physical possession is to be handed over on receipt of the balance sale consideration.

A list of questions has been sent to the developer.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.