News: MahaRERA Rejects Builder’s Plea on Landowner’s Jailing-10-02-2026

A developer near Mumbai who blamed court disputes and the imprisonment of the landowner for failing to secure an Occupation Certificate (OC) has been ordered by the Maharashtra Real Estate Regulatory Authority (MahaRERA) to hand over the flat and pay interest to the buyer.

The homebuyer purchased the flat through an agreement for sale executed in 2010 for about Rs 20 lakh. The agreement carried no possession date, though the buyer said the developer’s representatives had promised delivery within a year. When the project ran into legal trouble the developer offered a refund, which the buyer declined.

The buyer approached MahaRERA in 2020, complaining that on registering the project the developer had unilaterally pushed the possession date from the originally committed 2011 to 2017 and then 2019, and still had not delivered the flat with an OC. He sought interest for each month of delay from 2013, three years after booking, or alternatively interest at the State Bank of India’s highest marginal cost of lending rate (MCLR) plus 2% from the 2017 completion date declared to MahaRERA until realisation.

The developer countered that the agreement, executed under the Maharashtra Ownership of Flats Act, 1963, contained no possession date, that the buyer had accepted its terms without objection and that no time-bound commitment had been made. It said court cases, including a Civil Court injunction, had delayed construction through no fault of its own, and that buyers were repeatedly offered either a flat in another project or a full refund with interest. By choosing to wait, it argued, the complainant had waived any compensation claim.

On the OC, the developer said it applied in December 2018 but the authorities required the landowner’s signature. The landowner was in jail in an unrelated case and facing insolvency proceedings, so could not sign, and a request to waive the requirement had not been resolved.

MahaRERA was not persuaded. It directed the developer to hand over possession with the OC within 30 days of the order and to pay interest on the sale consideration at SBI’s highest MCLR plus 2 per cent per annum from 2013 until possession is actually delivered.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.