News: Wait Is Over, Second Flank Of Hero Honda Chowk Flyover Opens Today-24.07.2017

Wait is over, second flank of Hero Honda Chowk flyover opens today

TNN | Jul 24, 2017, 07:15 AM IST

Gurgaon: Chief minister Manohar Lal Khattar will inaugurate the second flank of Hero Honda flyover on Monday. The eight-lane flyover will boost connectivity and ease snarls for the commuters going towards Sector 10, Basai, Sultanpur lake and Jhajjar district.

The 1.4-km-long flyover was constructed as part of three-layer crossing — flyover, underpass and existing roads — at the Hero Honda Chowk.

Though the construction of the flyover was completed a few weeks ago, the national highway authority of India (NHAI) conducted load testing to ensure the safety parameters before it's opened to traffic. According to NHAI estimates, around 50,000 vehicles will use the flyover every day. "Since a majority of these vehicles will be crossing the stretch during the rush hour, it is pertinent that the load testing was successful," an NHAI official said.

The Delhi-Jaipur side of the flyover was opened to traffic on March 27 this year. However, it was used as the carriageway for Jaipur-bound traffic also. The construction of the four-lane underpass is still on, and the authority intends to open it for commuters by December 31 this year. In fact, work on the underpass and the flyover picked up pace after waterlogging led to massive snarls at the crossing in July last year.

"Besides the flyover, there will be 3.77km-long service lane. The flyover and service lane will cater to traffic coming from and going to Delhi, Gurgaon and Manesar. This will reduce the congestion for the daily commuters and bring relief to those living or working near the Hero Honda junction," said Ashok Sharma, project director, NHAI.


Construction of the Rs 197.84-crore project began in November 2014, and was expected to be completed by May 2017. But initially, it was slowed down due to delay in clearance of land required for the project. Litigation, and lack of coordination between departments, delayed the clearance of the land required for the project.

 

DISCLAIMER: This website and the Information contained is in the process of being updated and are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time the contents are fully updated the same shall not be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company. The Company is not liable for any consequence of any action taken by the viewer relying on such material/ information on this website.